1. Separate the two legal relationships
“Was it approved before settlement?” is not enough to determine who must pay a strata special levy. Ask both whom the owners corporation may pursue under the legislation, and how the buyer and seller allocated the expense under their actual contract.
The Strata Schemes Management Act 2015 governs contributions and relevant owner liability. Sale contracts may separately address regular levies, special levies and instalments. Special conditions can alter an ordinary clause. Memory of a previous standard contract is not an interpretation of this transaction.
Bring the complete signed contract, special conditions, resolutions, notices, payment records and current certificate. Identify who is making a demand and its legal basis. The owners corporation does not generally resolve the parties’ private sale-contract interpretation for them.
2. Distinguish resolution, levy and due date
Section 83 provides for levying a contribution by written notice specifying when it is due. Its notice provisions distinguish general contributions, urgent repairs and periodic arrangements. Read the applicable text rather than assuming every charge follows one timetable.
A discussion, budget approval, special-levy resolution, notice and payment deadline may occur on different dates. A resolution alone may not identify all instalments; an invoice alone may not explain the underlying decision or contract allocation.
Build a timeline covering the resolution, notice, each due date, exchange and settlement. Match amounts and project names. An estimated project budget is not necessarily an imposed contribution. Preserve later resolutions and revised notices so that a single screenshot does not conceal a material change.
3. A new owner may face existing unpaid contributions
Section 84(1) can make a new owner jointly and severally liable with a person already liable for a contribution, including relevant interest. A buyer should not assume the owners corporation is barred from pursuing a debt solely because it arose before the purchase.
That statutory position does not free a seller from a contractual promise to pay or allow an adjustment. A buyer may have a separate contractual claim, but that does not automatically suspend the owners corporation’s rights.
No particular debt is determined here. Examine transfer, levy, payment, certificate and other facts. “I only just moved in” is not a complete response, but neither should every amount be admitted without review. A later claim against a seller can involve cost and recovery risk, making accurate settlement arrangements particularly valuable.
4. Read this contract’s actual allocation
A clause may allocate liability by resolution, levy, due date or a defined category of instalments. Definitions, exceptions and special conditions matter. A friend’s transaction may have used different words.
Before exchange, ask how known unpaid contributions and proposed projects will be handled. If one party is to bear a specified cost, record the agreed arrangement in appropriate binding wording. A casual explanation may not amend the signed contract.
Clarify whether the arrangement requires actual payment, a settlement adjustment or another mechanism. An amount appearing in an adjustment statement and a cleared payment in the owners corporation’s account are not the same event. Read general and special clauses together, including any priority provision.
5. Understand the section 184 certificate
Section 184 covers specified information about contributions, unpaid amounts, dates, interest, capital works planning and other matters. Section 185 provides particular evidentiary effects for relevant purchasers for value concerning matters stated as at the certificate date.
The certificate is not a building-health guarantee or a prediction of every future repair. A later resolution, due date or payment may require updated information. Ask how much time is needed to request, obtain, read and, if necessary, correct a certificate.
If it appears inconsistent with minutes, identify the precise project and dates. Ask why a sum was or was not included. This article does not promise the same legal outcome for every omission. A certificate issued months before settlement should not be treated as a permanent guarantee that no additional cost will arise.
6. Analyse each instalment separately
One project may involve a total levy payable in several instalments, with a resolution before exchange and due dates either side of settlement. Neither “every later invoice belongs to the buyer” nor “every earlier resolution belongs to the seller” is a safe universal rule.
List the total, each instalment, notice and due date, payments, contractual allocation and intended settlement treatment. If a seller promises to pay a later instalment, consider an appropriate reliable mechanism with the representatives.
Do not assume a unilateral retention is lawful or that one retention model suits every sale. A future promise may be affected by disagreement, lack of funds or difficulty locating the seller. The buyer may need resources to address an external obligation even while pursuing a separate contractual right.
7. Look beyond this levy to the project
One adopted levy does not establish that the project is complete or fully funded. Read the scope, quotations, defects, reserves and capital works plan. Construction changes, insurance and disputes may affect the final cost.
Sections 182 and 183 concern access by appropriately entitled or authorised persons to records, including relevant financial and planning material. A records inspection provides context beyond the section 184 certificate, which has a different statutory function.
Reports have scope and date limits. “Not seen” and “does not exist” are different conclusions. Identify definite amounts, estimates and missing information. A manager’s optimistic forecast should not be treated as an engineering or legal guarantee.
8. Reconcile the settlement evidence
| Material | Question to resolve |
|---|---|
| Minutes and budget | What was decided, when, and was it amended? |
| Levy notice | Which project and instalment, with what due date? |
| Contract and special conditions | What definitions, allocation and exceptions apply? |
| Section 184 certificate | What did it state at its issue date? |
| Payment evidence | Was money received or merely said to have been transferred? |
| Settlement statement | Who pays externally, and how is the private allocation implemented? |
| Project records | Is the final cost known or is further funding possible? |
This original checklist organises evidence; it does not dictate a universal legal answer. Keep the final settlement statement and proof of payment. Assign unresolved questions and a follow-up date. If a later invoice arrives, compare whether it concerns an unpaid old amount, recording delay or a new contribution.
9. Hypothetical: one resolution and three due dates
Suppose a lot’s contribution under a special-levy decision is payable in three instalments, one before exchange and others around settlement. The illustration is fictional; the amount or sequence alone does not determine liability.
Compare two hypothetical contracts: one expressly assigns all instalments under a specified resolution to the seller; another allocates particular instalments by due date. The internal outcome may differ. Actual contracts may contain additional definitions and exceptions, so neither example interprets a standard form.
Then reconcile the owners corporation’s external account. Which instalments were imposed, which were paid, and who became owner? A private price adjustment without a clear payment arrangement may leave an external debt requiring attention. Do not assume a disagreement permits unilateral refusal to settle.
10. Hypothetical: an adjustment was made but the debt remains
Suppose the buyer received a settlement adjustment and later receives a demand because the owners corporation still records an unpaid contribution. This fictional example separates internal accounting from external payment.
Read the settlement statement, authority to pay, bank records and strata account. One arrangement may leave funds with the buyer to make payment; another may require the seller to clear the amount. The word “adjusted” does not resolve that distinction.
Investigate promptly, provide necessary payment evidence or request an explanation, and preserve rights against the other party where applicable. A recording delay is possible, as is a misunderstanding of the settlement arrangement. Do not attribute fault before checking or ignore an external due date because the private dispute remains unresolved.
11. Respond to collection while checking the amount
Sections 85–86 address matters including interest, payment plans and recovery, subject to statutory conditions and other requirements. This article does not exhaust the regulations or calculate every recovery-notice deadline.
Confirm the project, amount, period and liability; seek supporting records and discuss suitable payment or dispute options. A disagreement with a seller does not automatically suspend the owners corporation’s rights. Dissatisfaction with repair quality, a challenge to a resolution and an accrued payment obligation may require different legal pathways.
For a contractual claim, identify the actual clause and evidence of payment or demand. Do not turn a preliminary enquiry into an admission or a formal claim without understanding its effect. Obtain advice before withholding contributions on the assumption that another complaint or proceeding pauses all duties.
12. Verification scope and disclaimer
On 26 October 2026 the research read the official Strata Schemes Management Act version current from 26 August 2026, focusing on sections 83–86 and 182–185, alongside official NSW strata guidance. It did not exhaust regulations, standard-form editions, individual special conditions, transitions or cases.
This is general legal information. The examples do not allocate a real sale’s costs, establish that an omission extinguishes liability or authorise refusal to settle. Obtain advice on the complete documents before signing, settling, paying or taking dispute action. Reading or initial contact does not create a retainer. Historical levies and contracts may require earlier law. No unread case or individual reader’s contract is represented as reviewed.
Legal authorities & official further reading
A source-check date is not a certification that every amendment, authority or application has been verified. Read the specific verification notes.
Disclaimer
This article provides general legal information for public education only. It is not legal advice for any person, business or particular matter and should not be the sole basis for taking, or deciding not to take, action. Federal, state and territory laws differ and legislation, policy and case law may change. Read the article together with its jurisdiction, source-check date and verification limits. The appropriate approach depends on the particular facts, evidence, documents and applicable law; obtain independent advice about your own circumstances before making decisions. Reading this article, using this website or making preliminary contact does not establish a solicitor–client relationship. Acceptance of instructions and the scope of services must be separately confirmed. Do not send sensitive or confidential material before conflict checks and an appropriate document-submission method have been agreed. Seek prompt legal assistance for limitation periods, court deadlines or urgent matters; do not delay while waiting for a response. Nothing in this statement excludes or limits rights or liabilities that cannot lawfully be excluded or limited.